Ravensthorpe Nickel Project


Comet Resources has awarded the engineering, procurement and construction (EPC) contract to Multiplex Constructions for the development of its Ravensthorpe laterite nickel project. Multiplex has also been given a 180-day financing mandate to secure project funding. EPC Contract The EPC contract i...

Member and/or subscriber access only. Call (08) 9365 7455 for password help or click here to login.
| TOP
Murrin Murrin Expansion Project


Anaconda Nickel’s December 1998 Quarterly Report said subsequent to completion of the definition study, the company progressed with the preparation of a feasibility study for the Murrin Murrin Stage Two expansion project. In line with the objective of an expedited construction and control design, c...

Member and/or subscriber access only. Call (08) 9365 7455 for password help or click here to login.
| TOP
Golden Cities Gold Project


AMX Resources said the bankable feasibility study for the development of a standalone operation on the Havana Suva deposit at its Golden Cities gold project is scheduled for completion by June 1999. An infill drilling program at Havana Suva was completed. The results will be incorporated into the f...

Member and/or subscriber access only. Call (08) 9365 7455 for password help or click here to login.
| TOP
White Foil Gold Deposit


Mineral Commodities said it expected a definitive feasibility study for its White Foil gold deposit to be completed during the March 1999 quarter, upon which a decision to mine will be considered by the joint venture early in the following quarter. The company said a delineation/extension drilling ...

Member and/or subscriber access only. Call (08) 9365 7455 for password help or click here to login.
| TOP
Boddington Gold Mine


Normandy Mining’s December 1998 Quarterly Report said an updated resource estimate for Wandoo South at Boddington is nearing completion. It will incorporate results from an additional 110,000 metres of drilling carried out since the previous estimate of 311 million tonnes at 0.9 g/t gold and 0.1 pe...

Member and/or subscriber access only. Call (08) 9365 7455 for password help or click here to login.
| TOP
Gipsy/Rose/Lee Gas/Condensate Discoveries


Tap Oil said the Lee-1 exploration well, located 11 kilometres north-east of Varanus Island and three kilometres north of Rose-1, had been completed. The well discovered a significant quantity of gas and condensate and strong oil shows over an interval of 14-21 metres in the lower reservoir sands. ...

Member and/or subscriber access only. Call (08) 9365 7455 for password help or click here to login.
| TOP
Laminaria Oil Field, NT


Woodside Energy said it awarded the first major contract for the operation and ongoing maintenance (Phase Three) of the Laminaria and Corallina oil project in the Timor Sea. An Integrated Services Contract to the value of $35 million for the supply of operational and ongoing maintenance services to...

Member and/or subscriber access only. Call (08) 9365 7455 for password help or click here to login.
| TOP
Granites Gold Mine, NT


Normandy Mining’s December 1998 Quarterly Report said the feasibility study on the Callie/Granites operation was completed. The study recommended the construction of a new 2.5 million tonne per annum treatment plant at Dead Bullock Soak. The plant would be designed to allow for later expansion. T...

Member and/or subscriber access only. Call (08) 9365 7455 for password help or click here to login.
| TOP
Gawler Joint Venture, SA


Resolute Limited’s December 1998 Quarterly Report said indicated and inferred resources in the Challenger Area have been increased to 1.85 million tonnes of ore grading 8.45 g/t for 503,362 ounces of gold. Resolute said a new structural interpretation of the Challenger shoots, together with the rel...

Member and/or subscriber access only. Call (08) 9365 7455 for password help or click here to login.
| TOP
Pajingo Joint Venture, Qld


Normandy Mining’s December 1998 Quarterly Report said an expansion feasibility study on the Pajingo operation was completed during the December 1998 quarter. The study recommended an increase in gold production to more than 200,000 ounces per annum. Pajingo Resident Manager John McKinstry said th...

Member and/or subscriber access only. Call (08) 9365 7455 for password help or click here to login.
| TOP
Texas Silver/Gold Project, Qld


Macmin’s December 1998 Quarterly Report said the company planned to carry out preliminary metallurgical studies on the silver/gold resource at Texas with the objective of determining if some or most of the silver and gold can be recovered by way of a heap leach type operation. The study is schedule...

Member and/or subscriber access only. Call (08) 9365 7455 for password help or click here to login.
| TOP
Peak Hill Exploration Joint Venture Area, NSW


Alkane Exploration’s December 1998 Quarterly Report said several proposals to evaluate the feasibility of developing the Joint Venture’s sulphide deposit are being reviewed. A bioheap leach operation remains the favoured process option, particularly to develop the large, low-grade gold-copper resou...

Member and/or subscriber access only. Call (08) 9365 7455 for password help or click here to login.
| TOP
Way Linggo Gold-Silver Project, Indonesia


Meekatharra Minerals completed a feasibility study on its Way Linggo gold-silver project in southern Sumatra in 1996. At that time the project was shelved, but the company has now relaunched it after the completion of a revised feasibility study which showed Way Linggo to be viable despite depress...

Member and/or subscriber access only. Call (08) 9365 7455 for password help or click here to login.
| TOP
Dubbo zirconia project, NSW


Alkane Exploration’s December 1998 Quarterly Report said Perth-based industrial mineral consultant DEMA Pty Ltd has been appointed feasibility study manager for its Dubbo zirconia project.DEMA has proposed a three-stage feasibility program to be completed by the end of 1999.Phase One, which was comm...

Member and/or subscriber access only. Call (08) 9365 7455 for password help or click here to login.
| TOP